Future I-81 viaduct project construction ‘not expected’ to impact SU

I-81
The partial opening of the Van Buren Street roundabout near SU’s campus marks another important step in the I-81 viaduct project. Joe Zhao | Daily Orange File Photo

Have you had an experience with Syracuse University’s Title IX office? Share your story with The Daily Orange’s anonymous tip line.

With the partial opening of a new traffic circle near Syracuse University, another important step in the Interstate-81 viaduct project is now complete, marking the anticipated end of the construction’s impact on SU.

The Van Buren Street Roundabout partially reopened on Oct. 16 and restored direct connection from downtown to the Syracuse VA Medical Center and Crouse Hospital, SU and SUNY ESF. It also reopened a portion stretching from Irving Avenue to Waverly Place, which was formerly a one-way street due to construction.

“The partial opening of the roundabout at the intersection of Almond Street and Van Buren Street is an important step toward bringing the highway down to street level and removing the viaduct,” Sabrina Betts, a New York State Department of Transportation and communication specialist, wrote in a statement to The Daily Orange.

Betts also confirmed that while future work operations will take place throughout the project, requiring lane closures with flaggers during daytime hours, SU is “not expected to be impacted,” meaning a two-way traffic pattern will continue for “all future events” at the JMA Wireless Dome.

Construction on the roundabout began in April 2026 and is part of the city’s ongoing “Community Grid” project. Betts said it falls under Contract 5 within the viaduct project’s eight ongoing projects. It will serve as a “primary access point” to downtown Syracuse and help move traffic through the Southside, according to the NYSDOT website.

Contract 5 focuses on “creating a new gateway” to University Hill and helping construct a new interchange at I-690 at Crouse Avenue. The Community Grid is a $2.25 billion project intended to replace the existing I-81 viaduct with a street-level network and reconstruct Almond Street to include pedestrian and bicycle lanes, along with the Van Buren Street roundabout.

The project was first selected in 2019 and was originally projected to take six years to complete.

Proponents of the project hope it will reconnect the historically Black neighborhoods divided by the highway and create community “resiliency.”

The roundabout was initially planned to be near Dr. King Elementary School, sparking controversy from neighborhood residents and families. It was then moved to Van Buren Street.

The Community Grid project began construction in July 2023. The partial opening of the roundabout marks a major step in the project, Betts said. She also said alternating lane closures will take place during daytime hours to facilitate necessary work, beginning this fall.

Work on the Community Grid project is now expected to be finished mid-2027, while the I-81 Viaduct Project is predicted to be completed around 2031.